Representative list of current projects in 2011 include:
-
Homer Sewer Inspection and CIPP Rehabilitation; 30,000 feet of CCTV inspection and 18,000 feet of sewer main cured in place lining
-
Ted Stevens Anchorage International Airport Ramp Drainage Study; CCTV and manhole inspection of 30,000 feet of storm sewer pipe
-
Sewer Assessments in Rural Communities; assessments of sanitary sewers in Russian Mission, Brevig Mission, Ambler and other rural communities
-
Midtown Sewer Upgrade; 5,300 feet of sewer CCTV and manhole inspection and design of repairs
-
AWWU 2011 CIPP Water Projects; 2,500 feet of water main rehabilitation with a CIPP liner
-
University of Alaska Fairbanks Sewer CIPP Upgrades; condition assessment and engineering design of CIPP lining solutions for upgrading deteriorating wood stave sanitary sewer pipe on the Fairbanks campus
-
New Seward Highway Water Upgrade; 1,600 feet of 12" water main trenchless rehabilitation evaluation
-
AWWU Tidewater Gull Water Upgrade; installation of 3,000 feet of 16" PVC and DIP water main at the Port of Anchorage
-
East Airpark Storm System; design of three borings under roads, taxiways and railroad at the Anchorage Airport
-
Campbell Lake Manhole Rehabilitation; rehabilitation of a broken and leaking sanitary sewer manhole in Campbell Lake
-